FAQ

This is a brief list of common questions. If the answer to your question is not contained here, please contact us or use the online enquiry form.

  1. My existing cellar / basement has limited headroom and feels cramped. Will a basement conversion make a real difference to the feel of the space? Answer
  2. I’ve seen other basement conversions that feel a bit dingy. How will mine be different? Answer
  3. Do I need to get plans drawn up before beginning basement conversion? Answer
  4. How do I find out what permissions I might need? Answer
  5. Should I hire an architect or engineer and how do I find one? Answer
  6. When can we start and how long will it take to complete my basement conversion? Answer
  7. Will we need to move out during the works? If we stay, will there be much disruption? Answer
  8. How do I choose the fit out items for my bathroom or kitchen, and any other items like ironmongery etc? Do I need to purchase them myself? Answer
 

My existing cellar / basement has limited headroom and feels cramped. Will a basement conversion make a real difference to the feel of the space?

We typically design a basement to have at least 2.6 metres of finished headroom, more than your average London basement company would typically propose. We feel it is important to preserve the perspective of room size and height from the existing floors above so the new space doesn’t appear confined in comparison. If you have a period house, it is also likely you will have a step down to the rear part of the ground floor. We will ensure this step does not continue in the basement floor, giving you more flexibility with room layout and providing even more headroom at the front of the property.

I’ve seen other basement conversions that feel a bit dingy.
How will mine be different?

Waterproofing technology has come on leaps and bounds since the early cementious tanking systems were used to ‘block out’ the natural passage of water. Most modern conversions use a plastic cavity membrane system that allows the moisture to run uninterrupted behind the membrane into a sump beneath the floor, which is then pumped away into the drainage system. This means that no differential pressure is created either in the structure or across the membrane, and also that a vapour barrier as well as a water barrier is created between the earth and the structure.

Do I need to get plans drawn up before beginning my basement conversion?

For large structural projects detailed plans and specifications are a must as these enable us to provide accurate timescales and costs. They are also required for planning permission and for the engineer to work from. Please follow the link entitled ‘A Guide to Basements’ to learn more about these requirements and how we can help you.

How do I find out what permissions I might need?

Planning Permission

Planning permission is usually required for large structural alterations or additions to existing buildings, and the erection of new buildings. Planning permission is not required for all types of works, as some works are classed as ‘permitted development’. In the first instance, your council planning officer will be able to advise you as to which controls your work will be subject to. If we are contracted to undertake all pre-works arrangements for you, we will look after these issues and obtain all relevant permissions on your behalf.

Listed Building Consent

If your house is more than 170 years old, or of special architectural or historical significance, it may be Listed which means you will also require Listed Building Consent in order to carry out works. Such buildings are described as being either Grade I, Grade II* or Grade II in significance. This Listing potentially covers both the external and internal aspects of the structure. We will be able to advise you and seek the relevant permissions on your behalf. OLBC has expertise in these areas and we are a particularly good choice for your project if you have any specific concerns with regard to the safeguarding of any material of your property, or require any advice on sensitive restoration or conservation work.

Party Wall Awards

Party Wall Awards are usually required for major works to terraced or semi-detached houses and sometimes for detached houses too. You are required to arrange for a Party Wall Surveyor to agree an Award for the work before work begins on site. A Party Wall Surveyor is an independent professional who will draw up a condition report detailing the structure and condition of all properties concerned, and will include plans and engineering for the proposed project, and details of any specific clauses or precautions which must be taken during the work. Your neighbour is entitled to allow your Party Wall Surveyor to act on their behalf, or they may appoint their own Surveyor, a cost which would be passed on to you, as the proposer of the work. Party Wall Awards may not appear on the surface to be a large concern, but they can have a great impact on the time it takes to get a project onsite. We strongly recommend you contact us before appointing a surveyor so we may help you to minimize the problems that can occur. If we are contracted to undertake all pre-works arrangements for you, we will look after these issues and obtain all relevant permissions on your behalf.

Should I hire an architect or engineer and how do I find one?

If you have not already commissioned plans or engineering, we would encourage you to come direct to us for the entire ‘pre-works’ package. Not only can we offer you a cost-effective end-to-end service, we can free you of the responsibility of introducing professionals who may not have worked together before and may not share the same working approach. With our complete service the responsibility for delivering your project to site rests with our professionals who are experienced at working together to arrange basement excavation projects.

When can we start and how long will it take to complete my basement conversion?

The ‘pre-works’ element which is necessary to complete before work begins onsite will generally take from 3 to 4 months. In this time, we need to survey the site, agree plans for the basis of the new basement space, create a full quotation and specification, acquire planning permission, engineering, Party Wall awards, apply for street license and notify Building Control.

When on site the basic rule of thumb is to allow 16 weeks in the digging phase and around the same again for the structural and complete fit-out. There are many factors that can influence this average timescale, and you will be kept fully informed both before and during the project as to the timescale.

Will we need to move out during the works? If we stay, will there be much disruption?

If you are just excavating a basement in a house with suspended timber floors in most cases it is feasible to live in the house. If we are undertaking works beyond the basement, we usually recommend that the client vacate the premises. This has a positive effect on coat and duration, and is much nicer for the client. If we are only working underneath the house, it is highly likely that we can work with you in place. In this case we will seal any gaps in your ground floor to minimize the occurrence of dust, and keep all work areas screened off with our hoardings. Any work noise will be limited to our normal working hours. It would be unrealistic to suggest you wouldn’t notice we were there, but you should be able to continue using your ground floor as usual so disturbance should be minimal.

How do I choose the fit out items for my bathroom or kitchen, and any other items like ironmongery etc? Do I need to purchase them myself?

Our design team will arrange a series of meetings with you to develop a detailed specification for the entire project. Our role is to introduce you to the design possibilities and to find out what sort of look and budget you you’re your expectations. We will show you images of various general styles and finishes, and samples of wood floors and paint colours to help you take key decisions. We can also provide interior design at all levels of interaction. Use us just to help choose wall colours and tiles, or to design a specific piece of furniture, or for a complete cohesive scheme right down to cushions and artwork. Bespoke kitchens are also a possibility if you’re looking for something truly unique.

If you decide to choose the pieces yourself, we can suggest a number of sources for bathrooms, kitchens etc. that we would recommend.

We will supply all fit-out items, for which we make a small charge to cover the cost of administration, specification, delivery, storage and responsibility for suitability. This means that we become responsible for everything from ensuring everything is correct, suitable, and has appeared at the right time in full working order. It is necessary for us to maintain full control over this aspect of the work in order to provide you with fixed costs and time schedules for completion.

All images are of OLBC projects

Oxford and London Building Company (OLBC) Services : HomeBasement ConversionLoft ConversionKitchen ExtensionRestoration workInternal refurbishments

Areas covered - SW London & Surrey: Barnes SW14, Barnes Common SW13, Battersea SW11, Battersea Park SW11, Belgravia SW1, 
Between the Commons SW18, SW12, Chelsea SW10 & SW3, Clapham SW11, Clapham Common SW12, Earl’s Court SW5, East Sheen SW13,
 Eaton Square SW1X, Fulham SW6, Ham TW10, Hyde Park SW7, Kew TW9, Mortlake SW13, Parsons Green SW6, Pimlico SW1, 
Putney SW15, Putney Heath SW15, Roehampton SW15, Richmond TW9, South Kensington SW7, Sheen SE13, Southwark SE1, St James W1, 
Streatham SW2 & SW16,, Tooting SW17, Twickenham TW, Victoria SW1, Wandsworth Common SW18, Wandsworth SW18, Waterloo SE1, 
West Kensington, Westminster SW1, Wimbledon Common SW19, SW20, Wimbledon Park SW15, SW20, Wimbledon SW19 & SW20

West London : Bloomsbury WC1, WC2, EC1, Barons Court W6, Chiswick W4, Covent Garden WC2, Dukes Meadow W4, 
Fitzrovia W1, Hammersmith W6, Holland Park W11, W9, W2, Hyde Park W1, Kensington W8, Knightsbridge SW1, 
Ladbroke Grove W11, W9, Marylebone W1, Mayfair W1, Notting Hill W11, W9, Paddington W2, Park Lane W1, Piccadilly WC1, 
Richmond TW9, Richmond Park TW9, Shepherds Bush W6, W14, Soho W1, South Kensington SW7, West Kensington W14, Westminster W1

North London : Camden NW8, Dartmouth Park NW5, Hampstead NW3, Kentish Town NW5, Regents Park NW1, Primrose Hill NW8, 
South Hampstead NW6, St Johns Wood NW8

We are happy to work in Central London and the Congestion Charge Zone.

Site design by Helix Digital